The Council of the Borough of Bournemouth in this order called "the
autority" in pursuance of the powers conferred in that behalf by Section
60 [and 61] of the Town and Country Planning Act 1971 (as amended
by Section 10(1) of the TOwn and Country Amenities Act 1974), and
subject to the provisions of the Forestry Act 1967, hereby make the
following order:-
- In this Order:-
"the Act" means the Town and Country Planning Act 1971;
"owner" means the owner in fee simple, either in possession or who has granted a lease or tenancy of which the unexpired portion is less than three years; lessee (including a sub-lessee) or tenant in possession, the unexpired portion of whose lease or tenancy is three years or more and a mortgagee in possession; and
"the Secretary of State" means the Secretary of State for the Environment.
- Subject to the provisions of this Order and to the exemptions specified in the Second Schedule hereto, no person shall, except with the consent of the authority and in accordance with the conditions, if any, imposed on such consent, cut down, top, lop, uproot, wilfully damage or wilfully destroy or cause or permit the cutting down, topping, lopping, uprooting, wilful damage or wilful destruction of any tree specified in the First Schedule hereto or comprised in a group of trees or in a woodland therein specified, the position of which trees, groups of trees and woodlands is defined in the manner indicated in the said First Schedule on the map annexed hereto which map shall, for the purpose of such definition as aforesaid, prevail where any ambiguity arises between it and the specification in the said First Schedule.
- An application for consent made to the authority under Article 2 of the Order shall be in writing stating the reasons for making the application, and shall by refernece if necessary to a plan specify the trees to which the application relates, and the operations for the carrying out of which consent is required.
- Where an application for consent is made to the authority under this Order, the authority may grant such consent either unconditionally, or subject to such conditions (including conditions requiring the replacement of any tree by one or more trees on the site or in the immediate vicinity thereof), as the authority may think fit, or may refuse consent.
Provided that where the application relates to any woodland specified in the First Schedule to this Order the authority shall grant consent so far as accords with the principles of good forestry, except where, in the opinion of the authority, it is necessary in the interests of amenity to maintain the special character of the woodland or the woodland character of the area, and shall not impose conditions on such consent requiring replacement or replanting.
- The authority shall keep a register of all applicationis for consent under this Order containing information as to the nature of the application, the decision of the authority thereon, any compensation awarded in consequence of such decision and any directions as to replanting of woodlands; and every such register shall be available for inspection by the public at all reasonable hours.
- Where the authority refuse consent under this Order or grant such consent subject to conditions they may when refusing or granting consent certify in respect of any trees for which they are so refusing or granting consent that they are satisfied -
- that the refusal or condition is in the interests of good forestry; or
- in the case of trees other than trees comprised in woodlands, that the trees have an outstanding or special ammenity value.
- Where consent is granted under this Order to fell any part of a woodland other than consent for silvicultural thinning then unless
- - such consent is granted for the purpose of enabling development to be carried out in accordance with a permission to develop land under PartIII of the Act, or
- - the authority with the approval of the Secretary of State dispense with replanting,
the authority shall give to the owner of the land on which that part of the woodland is situated a direction in writing specifying the manner in which and the time within which he shall replant such land and where such a direction is given and the part is felled the owner shall, subject to the provision of this Order and section 175 of the Act, replant the said land in accordance with the direction.
- Any direction given under paragraph (1) of this Article may include requirements as to
- - species
- - number of trees per acre (hectare);
- - the erection and maintenance of fencing necessary for protection of the replanting;
- - the preparation of ground, draining, removal of brushwood, lop and top; and
- - protective measures against fire.
- On imposing any condition requiring the replacement of any tree under Article 4 of the Order, or on giving a direction under Article 6 of this Order with respect to the replanting of woodlands, the authority shall is such a condition or direction relates to land in respect of which byelaws made by a water authority since 31st March 1974, by any other authority (whose functions are now excercised by a water authority) whoat any time prior to 1st April1974 exercised the functions in respect of which the byelaw was made, by a drainage board, or by the Greater London Council in the exercise of its functions in relation to maintenance, improvement or construction of watercourses or of draingage works, restrict or regulate the planting of trees, notify the applicant or the owner of the land, as the case may be, of the existence of such byelaws and that any such condition or direction has effect subject to the requirements of the water authority, the drainage board, or the Greater London Council under those byelaws and the condition or direction shall have effect accordingly.
- The provisions set out in the Third Schedule to this Order, being provisions of Part III of the Act adapted and modified for the purposes of this Order, shall apply in relation thereto.
- Subject to the provisions of this Order, any person who has suffered loss or damage in consequence of any refusal (including revocation or modification) of consent under this Order or of any grant of any such consent subject to conditions, shall, if he makes a claim on the authority within the time and int he manner prescribed by this Order, be entitled to recover from the authority compensation in respect of such loss or damage provided that no compensation shall be payable in respect of loss or damage suffered by reason of such refusal or grant of consent in the case of any trees the subject of a certificate in accordance with Article 5 of this Order.
- In assessing compensation payable under the last preceding Arcticle account shall be taken of:
- any compensation or contribution which has been paid whether to the claimant or any other person, in respect of the same trees under the terms of this or any other Tree Preservation Order under Section 60 of the Act, or under the terms of any Interim Preservation Order made under Section 8 of the Town and Country Planning (Interim Development) Act 1943, or any compensation which has been paid or which could have been climed under the provision relating to the preservation of trees or protection of woodlans containes in an operative scheme under the Town and Country Planning Act , 1932, and
- any injurious affection to any land of the owner which would result from the felling of the trees the subject of the claim.
- A claim for compensation under this Order shall be in writing and shall be made by serving it on the authority, such service to effected by addressing the claim to the authority and leaving it at or sending it by post to the principal office of the authority.
- The time within which any such claim shall be made as aforesaid shall be a period of twelve months from the date of the decision of the authority, or of the Secretary of State, as the case may be, or where an appeal has been made to the Secretary of State against the decision of the authority, from the date of the decision of the Sectretary of State on the appeal.
- Any question of disputed compensation shall be determined in accordance with the provisions of Section 179 of the Act.
- The provisions of Section 61 of the Act shall apply to this Order and the Order shall take effect on 17th September 1976.
This Order shall apply to any tree specified in the First Schedule hereto, which is to be planted as mentioned therein, as from the time when that tree is planted.
NOTE: Any person contravening the
provisioin of this Order by cutting down, uprooting or wilfully
destroying a tree, or by wilfully damaging, topping or lopping a
tree in such a manner as to be likely to destroy it is guilty of
an offence and liable on summary conviction to a fine not exceeding
£400 or twice the sum which appears to the court to be the value
of the tree, whichever is the greater, or on indictment to a fine.
The penalty fo r any other contravention of this Order is a fine
not exceeding £200 on summary conviction and, in the case of a continuing
offence when the contravention is continued after conviction, a
person is liable on summary conviction to an additional fine not
exceeding £5 for every day on which the contravention is so continued.
If a tree other than one to which an Order
applies as part of a woodland is removed, uprooted or destroyed
in contravention of an Order or is removed, uprooted or destroyed
or dies at a time when its cutting down or uprooting is authorised
only by Section 60(6) of the Town and Country Planning Act 1971
relating to trees which are dying or dead or have become dangerous,
it is the duty of the owner of the land, unless on his application
the local planning authority dispense with the requirement, to plant
another tree of appropriate size and species at the same place as
soon as he reasonably can. Except in emergency, not less than 5
days' previous notice of the removal, etc., should be given to the
authority to enable the latter to decide whether or not to dispense
with the requirement.
|